Phase 1
January 13, 2016 | Collaborative Brain Trust EMP Orientation |
February 2016 | EMP Core Team Formed |
February 26, 2016 | EMP Town Hall I: Project Launch |
March 8, 2016 | EMP Town Hall II: Project Launch |
March 14-18, 2016 | EMP Work Groups Begin Meeting |
April 1, 2016 | EMP Town Hall III: Data Portfolio |
Phase 2
April 15, 2016 | EMP Town Hall IV: Strategic Initiatives |
April 27, 2016 | EMP Work Group Planning Matrices Due |
Phase 3
May 1-8, 2016 | EMP Final Writing/Editing |
Phase 4
May 17, 2016 | Classified Senate Vetting |
May 18, 2016 | CEMPC & College Council Vetting |
May 19, 2016 | Academic Senate Vetting |
June 2016 | Board of Trustees Approval |